Transport Program

Transport program

Lithgow City Council is responsible for 975km roads, 48 bridges, 130km of Footpaths & Cycleways and 279 kerb & gutter.   These are the projects we are currently working on.

Click on the plus sign to expand items for more details.

Planned

Atkinson Street/State Mine Gully Road, Lithgow

Project Start:  Tuesday 11th June 2024

Expected Completion: Friday 23rd August 2024

Phase: 

Update: 5 June 2024

NPWS are planning to undertake roadworks on the State Mine Gully Road access into the State Conservation Area. The nature of the works will mean that a full closure of State Mine Gully Road is required on weekdays, reopening on weekends. The works may take up to 10 weeks with the current start date planned for June 11th.

Visitors to the park are advised to use Old Bells Line of Road as their primary access to the park.

Key details

  • State Mine Gully Road will be closed on weekdays from Tuesday 11th June to Friday 23rd August 2024.
  • State Mine Gully Road will be open on weekends during this period (Open 6:00pm Friday to 6:00am Monday).
  • Visitors are advised to use Old Bells Line of Road as the primary access into the park instead.
  • Should there be any enquiries the contact from National Parks is Paul Huxley, 0409 936002 and Paul.Huxley@environment.nsw.gov.au

 


Update April 2024

This work has been scoped for inclusion as part of the broader Gardens of Stone development as the asset will require upgrade prior to the delivery of this project. The project has been costed at approximately $4million. The council continues to advocate for external State Government funding from the $50M allocated to Gardens of Stone to deliver this project.

Col Drew Drive – Renewal

 

Col Drew Drive Renewal  Project Start:
Expected Completion:
Funding  source: Grant Funded (LRCI Phase 4)
Phase:

Update: 
Hampton Road, Reseal

 

Rehabilitation and sealing of some sections of 4km Hampton Road between 

the 2 entrances to Norman Lee Road. The rehabilitation will include the road surface and subgrade, as required. 

Project Start:
Expected Completion:
Funding  source: Grant funded (FLR400287)
Phase:

Update:
Kirkley Street Roundabout – Traffic Island

 

Kirkley Street Roundabout Traffic Island  Project Start:
Expected Completion:
Funding  source: Grant Funded (LRCI Phase 4) 
Phase:

Update: 
New Disabled Parking Spaces

 

Construction of 4 x new accessible parking spaces including associated line marking, signage and kerb ramps.

  1. Roy Street, Lithgow, 
  2. Main Street, Wallerawang, 
  3. Wolgan Street, Portland 
  4. Williwa Street Portland 
Project Start:
Expected Completion:
Funding  source: Grant Funded (LRCI Phase 4)
Phase:

Update:
Portland / Sunny Corner Road – Bus Stop

 

Portland / Sunny Corner Road Bus Stop  Project Start:
Expected Completion:
Funding  source: Grant Funded (LRCI Phase 4)
Phase:

Update:
Stormwater Detention Basin – Mort Street

 

Renew kerb and gutter in various locations across the LGA (Local Government Area) that have been affected by tree roots, have come to the end of their life cycle or other damage. Project Start: 
Expected Completion: 
Funding  source: General Revenue/Grant Funded
Phase:

Update: 
Portland/Sunny Corner Road & Ilford Street, Portland – Traffic Island

 

Portland/Sunny Corner Road & Ilford Street, Portland Traffic Island  Project Start:
Expected Completion:
Funding  source: Grant Funded (LRCI Phase 4)
Phase:

Update:

Commenced

Coalbrook/Geordie Street (including Wear Street), Lithgow
Repair and renew the road pavement of Coalbrook Street, Geordie Street and Wear Street with a total length of approximately 1400 lineal metres. Note: this program is rolled over from 2022/23.

Project Start: 6 May 2024
Expected Completion: 20 May 2024
Phase: 
Update: 31 May 2024

Sealing is complete.  There is still work to be done to raise some of the service covers on Coalbrook Street and these will be done as soon as the contractor is available.

29/05/2024
Works will being this week to seal Coalbrook St.

 

17 May 2024
From Sunday 26th of May nightworks will commence on Coalbrook Street, Lithgow and are expected to run until Thursday 30th May. The works will occur between Davy Street and Sandford Avenue. All works will be night shift except for Monday daytime where the spray seal will be applied. 

Residents are asked that they park their cars either in their driveways or off Coalbrook Street to allow the works to be completed. There will be traffic controllers on site so if cars need to be moved residents can talk to them at the time.

Works will start at 7.00pm and be completed by 6.00am for the night shifts and the day shift will be between 7.00am and be completed by 5.00pm.

07 May 2024Coalbrook Street Lithgow- Nightworks commencing Sunday, 12th May. 

 Roadworks will be commencing on Sunday night, 12th May at 7pm on Coalbrook Street between Davy Street and Sandford Avenue.  Weather permitting, the work will be completed by Thursday, 16th May.  

 The works include the profiling of the edge of the road near the gutters, laying a 10mm spray seal over the width of the road and then a layer of asphalt to top that. All works will be night shift except for Monday daytime where the spray seal will be applied.   

 Works will be undertaken between 7.00pm and 6.00am for the night shifts and the day shift will be between 7.00am and 5.00pm.  

 Residents are asked to park their cars either in their driveways or off Coalbrook Street to allow the works to be completed. There will be traffic controllers on site, so if cars need to be moved residents can talk to them at the time.   Council acknowledges the inconvenience to residents in Coalbrook Street while these important works are being undertaken and thanks them for their patience.  

 Should there be any enquiries regarding the above works contact Paul Creelman, Transport Manager, at Lithgow Council on 6354 9999. Any enquiries during the work shifts can be directed to the traffic controllers or staff working on site.  

16 April 2024
Prices are currently being finalised for works on Coalbrook Street, Lithgow. Once confirmed and pending contractor availability work will be scheduled to commence for work to be undertaken between the Native Plant Nursery to Stephenson Street.

Coxs Street Lane, Portland

 

Renewal of 175m of road. 

Project Start:
Expected Completion:
Funding  source: General Revenue
Phase:

Update: 18 Oct 2024

Rehabilitation has been completed.  Sealing will commence in 2-3 weeks (weather permitting)

23 July 2024Council Tender awarded tender for bitumen spray seal servicesMinute No. 24-158 – Council meeting 22 July 2024 

Geordie Street Causeway - replacement

 

(Resources for Regions Round 9)

Commission a feasibility analysis and detailed design of a concrete,

single span bridge to replace the existing concrete causeway on Geordie Street, Lithgow.

Project Start: 1 January 2024
Expected Completion: July 2024
Phase: In progress
Update: 4  April 2024
Request for quotations to undertake the Feasibility and Options Study has closed.

The quotations are being assessed and will be awarded following assessment determination.

The Draft Feasibility and Options Study is expected to be finalised and community consultation undertaken during the July – September Quarter.

Glen Davis Causeway - replacement

 

  • Detour and construction
  • Causeway repair and construction (subject to grand funding approval)
Project Start: 1 July 2023
Expected Completion: Ongoing
Phase: In progress
Update:
Detour and construction:  The cost to construct was exceedingly higher than the amount allocated ($500k) from the natural disaster funding.  The funds have been reallocated to other priority projects consistent with the grant funding guidelines.  The community will be consulted on an alternative option. (Q2 Budget review – Council Meeting 26 Feb 2024 – Min. No. 23-34) 

Causeway repair and construction:  The council has submitted an application for replacement of the Glen Davis Causeway bridge for $2,122,836 under Disaster Ready Fund Round 2 and is awaiting advise on the outcome of this application.

General Asset Stormwater Maintenance Program - Diverting water from roadways

 

  • Urban kerb & gutter replacement 
  • Rural roadsides drain reformation 
Project Start:
Expected Completion:
Funding  source: Special Rate Variation
Phase:

Update: 09 August 2024
McKanes Falls Road, South Bowenfels – works will start on McKanes Falls road in the week starting 19th August to reinstate drainage lines and repair the road surface. These works will take approximately 4 weeks and road users are asked to take care during this time as traffic control will be in place. 
General Asset Transport Maintenance – Enhanced evidence-based management

 

  • Sealed Road Condition 2 Preventative Maintenance 
  • Sealed Road Condition 3 Preventative Maintenance 
  • Sealed Road Condition 4 Preventative Maintenance 
  • High risk road safety signage & barrier improvements 

. 

Project Start:
Expected Completion:
Funding  source: Special Rate Variation 
Phase:

Update:
High Street, Portland

 

Stabilisation and renewal of 5020m of road from Williwa Street to Roxburgh Street. 

Project Start: 26 August 2024 (weather permitting)
Expected Completion: Approximately 4 weeks
Funding  source: Special Rate Variation 
Phase: Commenced
Update 24 Sept 2024
Works on High Street, Portland have been completed with line marking to take place in the next few weeks.

17 Sept 2024

On Thursday 19th September, High Street Portland, Between Roxburgh and Williwa Streets, will be closed from 7.00am to 4.30pm for road sealing.

Residents along this stretch of road will be able to access their properties but will need to let the traffic controllers know as they are about to leave/arrive.

There will be detours in place for traffic to go around the site, minor delays can be expected.

This will conclude the major works for this section of road, with line marking to occur over the next few weeks to finalise the works.

Should you have any questions please contact Council on 6354 9999.

Update: 09 August 2024 
Capital works are due to start on High Street, Portland between Williwa Street and Roxburgh Street on the 26th of August, (weather permitting). This will include the rehabilitation and stabilisation of the road pavement.  A single coat seal will be applied over the area for a few weeks while it settles. The road will then be sealed once the road pavement is ready.

The works will take approximately 4 weeks during which time residents are asked to not park on the road shoulders between 7.30 and 5.30pm, Monday to Friday.

Residents in High Street will receive a detailed letter prior to works commencing.

Update: 23 July 2024 The council awarded the tender to Duke’s Earthmoving and Excavation P/L for reconstruction servicesMinute No. 24-160 – Council meeting 22 July 2024 

Blackmans Creek Road, Hartley – Renewal

 

Renew road, from Great Western Highway to end, (2600 metres), with 1500 metres sealed and 1100 metres unsealed. The sealed section will be resealed in a 20/10 2 coat seal with the unsealed section being regraveled with DGB20.   Project Start:
Expected Completion:
Funding  source: General revenue
Phase:

Update: 18 Oct 2024

 

The old road surface has been removed and road base is being imported to build up the road which in preparation for sealing.

Update 24 Sept 2024
Works are due to start on Monday 30th September on Blackmans Creek Road to fully resheet the road and reseal the road from the Great Western Highway to the turning circle. The road will be closed to all but local traffic for the works, Monday to Friday, 7.00am to 4.00pm. Drainage works have occurred over the previous 3 months which will shorten the length of works.
23 July 2024
The council awarded the tender for bitumen spray seal servicesMinute No. 24-158 – Council meeting 22 July 2024 

Lithgow Street, Lithgow - Renewal

 

The renewal of Lithgow Street, Lithgow, from Proto Avenue to Mort Street. A distance of 450 metres and 6000 square metres. This project will see the removal of the current road surface and replaced with a new surface with the renewal of line marking and any signage that needs replacing. 

Project Start: 29 Sept 2024
Expected Completion: 2 weeks
Funding  source: Special Rate Variation
Phase:

Update: 18 Oct 2024

Line marking has been booked and will be undertaken as soon as the contractor is available. 

24 Sept 2024

Lithgow Street resealing- The Lithgow Street reseal, between Proto Avenue and Mort Street will be commencing on Sunday 29th September at 7.00PM and be running for the following 3 and possibly 4 nights. The road will be closed in sections to allow traffic to flow during the works.  Once these works have been completed the road will be line marked in the following 2 weeks.

23 July 2024
The council awarded the tender for asphalt resealing servicesMinute No. 24-161Council meeting 22 July 2024.

Limestone Creek Road, Portland – renewal

 

  • Reseal 400m. 
  • Seal 450m. 
Project Start:
Expected Completion:
Funding  source: Grant funded (Roads to Recovery)
Phase:

Update: 23 July 2024
The Council awarded the tender for bitumen spray seal servicesMinute No. 24-158 – Council meeting 22 July 2024
Main Street / Cupro Street - Stormwater Drainage improvement

 

Triplication of stormwater infrastructure capacity from Main Street to Farmers Creek. 

Stage 1: Installation of two new 900mm concrete pipes from Farmers Creek through to the rail line. 

Stage 2: Under boring of the rail line to connect Stage 1 of the project through  to an array of new inlets on Main Street

Project Start: 
Expected Completion:
Funding  source:Grant funded (Resources for Regions Rd 9)
Phase:

Update: 23 July 2024

The Council awarded the tender to Keane Civic and Construction for the construction of new stormwater pits and pipesMinute No. 24-157Council meeting 22 July 2024 

Maintenance Grading

 

Maintenance works to gravel roads 

Phase: In progress
Update: 18 Oct 2024

Grading has been completed on Old Bindo Road, Biddys Pinch Road and Jerrys Meadows Road. Works are continuing on Genowlan Road and Huntingdale Road which should be completed within the next 2 weeks, the grading team will then be moving onto the unsealed roads in Glen Davis.

 

The shoulder slashing will be continuing on the Portland Cullen Bullen Road and will be continuing on other roads in the area.

24 Sept 2024
Grading works have been complete on Blackheath Creek Road, Old Bindo Road, Jerrys Meadow Road and Anarel Road. Grading is continuing on Genowlan Road Glen Alice and will be starting on Biddys Pinch Road, Hampton soon.

 

09 August 2024
Grading work is continuing in the following locations

  • Genowlan/ Huntingdale Roads, Glen Alice
  • Jerry Meadows Road, Sodwalls
  • Various roads in the Hartley Valley
  • Marsden Swamp Road
  • Clarke Simpson Road, Kanimbla Valley

31 May 2024
Maintenance grading is being conducted on Honeysuckle Falls Road, Sodwalls Road and in the Capertee Valley on Nile Road followed by Dunville Loop.

29 May 2024
Maintenance grading is being conducted on Honeysuckle Falls Road, Sodwalls Road and in the Capertee Valley on Nile Road.

17 May 2024
Grading is taking place on Honeysuckle Falls Road and in the Capertee Valley.

7 May 2024 – The grading team has completed the current program of works in the Glen Davis area.  Work will commence in the Rydal area

 

Martins Road, Rydal – Renewal

 

Regraveling and sealing 1.5km of road  Project Start: 25 Sept 2024
Expected Completion: 5-6 weeks weather permitting
Funding  source: Grant funded (Roads to Recovery) 
Phase: Commenced Update:

18 Oct 2024Works will begin on Martins Road, Rydal on Wednesday 25th September with the road being closed Monday to Friday, between 7.00am to 4.00pm to all but residents. The road will have the drainage lines reinstated, the road resheeted and the road resealed from Magpie Hollow Road to Hampton Road. The works are expected to take 5-6 weeks, weather permitting.

Update: 24 Sept 2024Works will begin on Martins Road, Rydal on Wednesday 25th September with the road being closed Monday to Friday, between 7.00am to 4.00pm to all but residents. The road will have the drainage lines reinstated, the road resheeted and the road resealed from Magpie Hollow Road to Hampton Road. The works are expected to take 5-6 weeks, weather permitting.

23 July – The council awarded the tender for bitumen spray seal servicesMinute No. 24-158 – Council meeting 22 July 2024 

Stormwater Detention Basin – Mort Street

 

Remove the current road seal, repair any road failures as required, build up with road base and reseal 350m road from Williwa Street to Dulhunty Street. 

Project Start:
Expected Completion:
Funding  source: Grant Funded (Roads to Recovery) 
Phase:

Update: 23 July 2024

The Council awarded the tender for bitumen spray seal servicesMinute No. 24-158 – Council meeting 22 July 2024 

Pothole Repair Program

 

Pothole Repair Program 

Project Start: Ongoing
Expected Completion:
Phase: In progress
Update: 18 Oct 2024

Road patching will be occurring on Magpie Hollow Road, Hampton Road, Glen Davis Road, Glen Alice Road and Sodwalls Road, as well as other locations as required.

17 May 2024Council has been working on roads in the Tarana area, repairing damaged road surfaces on Sodwalls, Diamond Swamp and Tarana Road. Works are currently occurring on Glen Alice Road which are expected to be completed mid-next week.April 2024
Pothole repairs are continuing with a focus on the Tarana area (including Sodwalls Road and Diamond Swamp Road), Range Road and Pipers Flat Road.

Regional Roads Safety Improvements Program

 

(Resources for Regions Round 9)
Reconstruct/upgrade regional, high-priority road assets.

 

Project Start: Ongoing
Expected Completion:
Phase: In progress
Update: 31 May 2024The urgent works on Pipers Flat Road have also been completed. The sealing and with the associated drainage works should go a long way to preventing this happening again.

29 May 2024

Urgent roadworks on Pipers Flat Road Wallerawang were undertaken on Monday.

17 May 2024
Works on Pipers Flat Road are expected to be completed on Friday 17th May, with the sealing of this section to occur as soon as the contractors are available.

Regional Roads Safety Improvements Portland/Sunny Corner Road

 

Scope of works 2 main areas of road totaling 3200m includes: 

  1. Widening of road to 9 meters 
  2. Drainage works. 
  3. Stabilized pavement with 3% cement 
  4. 2 coat 20/10 Bitumen seal 
  5. Line marking. 
  6. Guideposts

Project Start:
Expected Completion:
Funding  source: Grant funded (Resources for Regions Rd 9)
Phase:

Update: 18 Oct 2024

The road has been sealed from the Great Western Highway to the LGA boundary. Line marking has been booked and will be undertaken as soon as the contractor is available.

23 July 2024 

 

The Council awarded the tender to Gracey’s Earthmoving and Excavation P/L for reconstruction servicesMinute No. 24-160Council meeting 22 July 2024 

Cox's River Road

 

Roads to recovery program

 

Project Start: Ongoing
Expected Completion:
Phase: In progress
Update:  09 August 2024 The earthworks on Coxs River Road near the Duddewarra Bridge have been completed.  The site will be left for a few weeks for the stabilised area to settle. Sealing of the site will then take place completing the works.

Update: 31 May 2024 Works have started on Coxs River Road as a part of the Roads to Recovery program, these works will repair the road pavement, clear the open drains at the side of the road and reseal the road through to the Dudewarra bridge. Sealing may be delayed due to the temperature but will be sealed as soon as the temperatures rise.

Rural Roadside Drain Reformation Program

 

Diverting water from roadways Project Start: 1 July 2024
Expected Completion: 30 June 2025
Phase:
Update: Underway

Completed

Musket Parade, Lithgow Renewal

 

Musket Parade, Lithgow Renewal  Project Start:
Expected Completion:
Funding  source: General Revenue/Special Rate Variation
Phase: Completed

Update: 23 July 2024

 

The council awarded the tender for asphalt resealing servicesMinute No. 24-161 – Council meeting 22 July 2024 

Hill Street, Lithgow – Renewal

 

Hill Street, Lithgow Renewal  Project Start:
Expected Completion:
Funding  source: Grant Funded (Roads to Recovery) 
Phase: Completed

Update: 23 July 2024

 

The council awarded the tender for asphalt resealing servicesMinute No. 24-161 – Council meeting 22 July 2024 

Kremer Crescent, Wallerawang – Renewal

 

Kremer Crescent, Wallerawang Renewal  Project Start:
Expected Completion:
Funding  source: General Revenue
Phase: Completed

Update: 23 July 2024
The council awarded the tender for asphalt resealing servicesMinute No. 24-161 – Council meeting 22 July 2024 
Anarel Road, Sodwalls

 

Re sheeting Anarel Road with road base and improving the drainage of the road  Project Start: 
Expected Completion: March 2023
Phase: Completed
Bells Road over Ida Falls Creek

 

Construction of a concrete barrier to protect an exposed watermain.  
 (Q2 Budget review – Council Meeting 26 Feb 2024 – Min. No. 23-34)

Project Start: 2023
Expected Completion: March 2023
Phase: Completed
Jerrys Meadow Road, Sodwalls

 

Reseal and remediation of sections of pavement. Project Start: 
Expected Completion: March 2023
Phase: Completed
Kerb & Gutter Renewal Program - Diverting water from roadways

 

Renew kerb and gutter in various locations across the LGA (Local Government Area) that have been affected by tree roots, have come to the end of their life cycle or other damage. Project Start: 25 March 2024
Expected Completion: 21 June 2024
Funding  source: Special Rate Variation
Phase:

Update: Underway
Kanimbla Drive & Megalong Place, Kanimbla

 

Reseal and remediation of sections of pavement. Project Start: 
Expected Completion: 22 March 2024
Phase: Complete
Update: Council has completed major drainage works and the sealing of Kanimbla Drive and Megalong Place.Despite being disrupted by damage from storms, which added to the time and complexity of the project, the sealing work was completed 21- 22 March.
Line Marking - Various locations

Project Start: 9 April 2024 

Expected Completion: 10 April 2024 (weather permitting) 

Phase: Complete 

Update:  

Line marking to establish or re-establish the centre lines, edge lines and some give way lines (depending on the location) was completed in the following locations. 

  • Bridge Street, Lithgow 
  • Inch Street, Lithgow 
  • Amiens Street, Lithgow 
  • Magpie Hollow Road, South Bowenfels 
  • Coxs River Road, Hartley 
Peach Tree Road, Megalong Valley

 

Re-gravel & seal road.  Project Start: December 2023
Expected Completion: January 2024
Update: Complete
Roads Renewal SRV Program

 

Sunny Corner Road Portland (470m From Sofala to Falnash St) Project Start: 11 March 2024
Expected Completion: 12 April 2024
Phase: Completed

 

Corderoy Place, Wallerawang (full length 75m)  Project Start: 4 November 2023
Expected Completion: 16 November 2023
Phase: Completed

 

Main Street, Wallerawang (Blackberry Lane to Railway line – 1120m) Project Start: 11 November 2023
Expected Completion: 20 November 2023
Phase: Completed
Roads Renewal SRV Program

 

Brays Lane, Wallerawang (Blackberry Lane to No. 75 – 1200m) Project Start: 26 March 2024
Expected Completion: May 2024
Phase: In progress
Updates: 31/ May 2024

Sealing is now completed.

17 May 2024: Works continue on Brays Lane with the current site still affected due to decent rainfall, preparation for sealing has been delayed until the site dries out sufficiently enough for sealing work to commence.

 

7 May 2024: Sealing of the road is scheduled to be undertaken in the next 2 weeks (weather permitting).

16 April 2024: Sealing to be undertaken within the next 3-4 weeks (weather dependent)

4 April 2024: Work has commenced with the old road surface being removed, road base is being added in preparation for sealing.

26 March 2024: Works will commence on the rehabilitation of the road base and reseal of Brays Lane.  The works will run from Blackberry Lane to house number 137 and access to this section of road will be for residents only during work hours, 7.30 am to 4 pm Monday to Friday.

Saville & Purcell Street, Portland

 

Repairs and renewal. Project Start: 5 August 2023
Expected Completion: 26 September 2023
Phase: Completed
Wolgan Road, Lidsdale

 

Works to improve the stormwater drainage system and rehabilitate Wolgan Road between Ian Holt Drive and Maddox Lane 

Project Start: 8 April 2024
Expected Completion: End of May
Phase: In progress
Hours of Roadwork Operation: 7.00am to 4.30 pm – residents and motorists may experience minor delays due to the works.
Update: 31 May 2024

Sealing is now completed.

17 May 2024

 

Road works are continuing on Wolgan Road with footpath works expected to be completed by the end of next week. Sealing dates for this road have been pushed back due to the recent rainfall, contractor availability will determine when the sealing commences.

Tuesday 7 May 2024The road works are well underway with sealing of the road scheduled to be undertaken in the next 2-3 weeks (weather permitting). The drainage works are complete and the minor footpath modification will be completed in the next week.

Tuesday 16 April 2024
The upgrade of the stormwater infrastructure is complete.  Works to start on the footpath improvements week ending 19th April.  Once footpath improvements are complete the road works will commence (weather dependent).

Update 8 April 2024
Works will start on the stormwater drainage, improving the flow of stormwater away from properties and reducing it across footpaths. Once the stormwater/footpath works are completed the work on rehabilitating the road will commence.

7.00am to 4.30pm, Monday to Friday.

Residents and motorists may experience minor delays due to the works