Lithgow Main Street Restoration – Stage 2

Project Description

Stage 2 of the Lithgow Main Street Restoration Project. 

This project proposes to build on the works already completed in Stage 1. The scope of this phase of the project will include the replacement of the section of footpath between Bridge Street and Eskbank Street. 

The original scope of works included works on both the southern and northern sides of the Main Street (between Bridge Street and Eskbank Street) however, based on the limited budget, the scope was reduced to include only the northern (railway line) side of Main Street, the raised pedestrian crossing and part of Bridge Street (from the crossing toward Main Street Lane).   This project split was carefully considered to enable works to be undertaken without impacting future stages and providing safe transition from the new works to the remaining footpath and kerb on the southern side.   

As the design has been completed, and costs are known for the rest of the works (southern side of the Bridge to Eskbank Street block), Council is searching for funding opportunities and is ready to make applications as soon as suitable opportunities arise.  Once this funding is secured, Council will be further seeking funding for Stage 3 works (from Eskbank Street to Cook Street Plaza).  

 

Project Updates

 

Program update Friday 11 April 2025

Plants have been installed in the at the Bridge Street end garden. New concrete kerb installed and concrete base for bluestone pavers and recycled brick banding up to psychedelic skin tattoo studio have been installed. The kerb from psychedelic skin tattoo studio shops up to the northern access of Higgins Solicitor’s commenced this week and the bluestone and brick banding base due is to be poured next week. The contractors will tidy up the existing works prior to Easter weekend and will cease work until the 28th of April to reduce the impact on residents businesses and visitors over the holiday period.

 

Program update Friday 4 April 2025

Work is continuing to progress.  Council’s contractors are working with business to minimise disruption.

Paving and brick bandings have been installed including sealing and backfill.

Leading to Easter ANZAC holiday period the focus will be on completing current stages under construction to provide safe surfaces for pedestrians, local businesses and visitors to Lithgow.

 

Program update Thursday 27 March 2025

As per schedule, concrete base has now been formed and poured for Bluestone paving and recycled brick banding. Concrete footpath from Mountain Gum Tuition up to Hairdressers has now been excavated, prepared and concrete poured on Thursday 27th March as per program.

Topsoil has been installed place in the garden at Bridge Street after erosion was noticed which means plants can now be planted in the garden bed.

Demolition of existing brick kerb will commence on Friday in front of Missy Peter’s Hairdressers and up to Psychedelic Skin Tattoo pending favourable weather.

Contractors will prepare to form and pour a new concrete kerb approximately from Wednesday 4th April. With the footpath excavation and preparation to continue following the installation of the kerb.

 

Program update Thursday 20 March 2025

This week a new section of kerb was installed.  The construction of the pavement has been impacted by concrete supply however the construction team used the opportunity to clean up the site, reinstall the bus shelter and install steel edging. Pouring of pavement surface will continue week starting 24th March.

 

Program update Thursday 13 March 2025

Works have progressed well despite having to adjust work zones due to business access.
Paving and brick bandings have been installed including sealing and backfill.

The pavement, kerb and utility adjustments have been completed in front of the Lithgow Valley Film Society, Khai Beauty, Samsara Wellness and Massage, Lithgow Conveyancing Company and Sparks Finance.

Brick banding, brick headers and granite paving has been installed has been installed from the corner of Bridge Street and Main Street to the Lithgow Valley Film Society

Works between Missy Peters Hair and Euphoric Utopia are forecasted for mid-to-late March and expected to conclude Mid-April.

 

Program update Friday 7 March 2025

Blue stone paving has now been installed from Bridge street, alongside the kerb on Main street & turns up towards the toilet block, then adjacent the shop fronts up to the Thai Massage. Grouting to follow.

Recycled brick paving has now been installed to side of path along side of the park, in & around the path to the public toilet block, & banding up to Thai massage, grouting is currently underway.

Concrete kerb & paver base has been extended beyond the front door of Lithgow Community projects in order to reduce access inconvenience.

The Concrete path from Thai massage to Lithgow Community projects has been poured.

Top dress soil to park & soil to garden beds as required on Friday 7 March.

Paver to return to site Tuesday 11-3-25 & complete Blue stone paving up to Lithgow Community Projects, & complete recycled brick paving up to Lithgow Community Projects.

 

Program update Friday 28 February 2025

This week Telstra was onsite ensuring that pits are adjusted in readiness for the new pavement.

The black granite paving and brick headers have been received onsite, and installation will commence on Monday 3 March.

As the works progress the contractors are continuing to work with the businesses to ensure minimal disruption to them and their clients.

March 3-7 –
Brick Banding and Granite paving – Bridge/Main Street intersection, Pioneer Park and Lithgow Valley Cinema.
Concrete kerb and pavement installation – Lot 5.

March 7 – 21
Lot 6 (Lithgow Family Support and Lithgow Community Projects)  Concrete kerb and pavement works, pit adjustments, vehicle crossing, trafficable pavement and kerb/pram ramp.

 

Program update Friday 21 February 2025

The Kerb and footpath has been replaced between the intersection of Bridge and Main Streets and Samsara Wellness and Massage.

Kerb removal and replacement will commence on 24 February in front of Lithgow Valley Film Society, Khai Beauty, Samsara Wellness and Massage, Lithgow Conveyancing Company and Sparks Finance.  Footpath replacement for this section will commence 3 March.

Installation of the brick banding, brick header and border paving to commence on 3 March.

 

Program update Friday 14 February 2025

Whilst the wet weather event on Monday 10th caused a delay in the concrete pour, the project is continuing to move forward.

Works are progressing on track at the eastern end near Bridge Street, new footpath has been installed along pioneer park including the path to the toilet block. Surfaces backfilled and levelled off to make safe – remaining landscaping to be done towards the end of the project to avoid vandalism and synchronise landscaping with the other areas yet to be built.

The existing kerb and paved footpath from the edge of Pioneer Park towards the Lithgow Valley Film Society and Samsara Wellness and Massage Centre are in the process of being removed and replaced with new concrete finishes.

The kerb and footpath replacement works are occurring in block segments along Main Street from Bridge Street to Eskbank Street to minimise disruption to businesses, and vehicle and pedestrian traffic.

 

Project Update 7 February 2025

The concrete footpath has been poured, asphalt road infill and kerb installed from the Corner of Bridge and Main Street to the toilet block.

Final filling of the garden bed at the intersection of Bridge & Main Streets, along with planning and paving to be completed at a later date.

Telstra pits have been adjusted to suit new levels.

Upcoming works

  1. Make good paths and surfaces from the park to the crossing.
  2. Demolish old kerb line and install new kerb, remove the pavers and prepare the base in front of the Lithgow Valley Cinema and Samara Wellness and Massage.

Council’s contractors are working with business to minimise disruption and ensure they are accessible.

 

Project Update 28 January 2025

Works are progressing on track at the eastern end near Bridge Street, with the permanent construction of the traffic island and completion of the new stormwater drainage pits completed.

The existing kerb and paved footpath from the bridge through to Pioneer Park are in the process of being removed and replaced with new concrete finishes.

The kerb and footpath replacement works will occur in block segments along Main Street from Bridge Street to Eskbank Street to minimise disruption to businesses, and vehicle and pedestrian traffic.

The current work is detailed on the map below:

 

Project Timeline

icondescription
dot

Community Feedback Open

19 February 2024

dot

Community Feedback Close

24 March 2024

dot

Construction Tender Open   

September 2024 

dot

Construction tender close

October 2024

dot

Survey works  

December 2024 

dot

Construction Commencing   

December 2024 

circle

Expected Completion  

End of June 2025  

Lot Business/s Date
Lot 1 Corner Bridge St and Main Street Completed 31 January
Lot 2

Pioneers Park

Note: Garden bed partial fill as we plan to complete fill and planting towards the end all together paving remains due early March

Completed 7 February
Lot 3 Pioneers Park Jan 30 – Feb 7
Lot 4 Lithgow Valley Film Society Feb 10 – Feb 21
Lot 5

Khai Beauty

Samsara Wellness and Massage

Lithgow Conveyancing Company

Sparks Finance

Feb 24 – Mar 7
Lot 6 Lithgow Family Support and Lithgow Community Projects Mar 7 – Mar 21
Lot 7

LINC

Vacant Shop

Missy Peters Hair, Lash Eclaire, Hair by Rachel Cameron

Mar 10 – Mar 28
Lot 8

Link Wentworth,

Tattoo Shop

Euphoric Utopia

Vacant shop

Mar 21 – Apr 12
  Prepare Main Street for Easter Period Apr 14 – Apr 17
  Easter /ANZAC Trading Apr 18 – Apr 28
Lot 9

Barry F Cosier Solicitors & Associates

Olivers Criminal Lawyers

Lithgow Legacy

Higgins Lawyers

Hometown Cafe

Apr 28 – May 16
Lot 10 Bridge Street – Initial section on the Southern Side May 19 – May 30
Lot 11 Old Courthouse Hotel, Laing & Simmons Property, Emerald Lantern Chinese – Includes pedestrian crossing works Jun 3 – Jun 30

Frequently Asked Questions

Please see list of FAQs below.  If your question is not answered here, please contact the Project Officer via email council@lithgow.nsw.gov.au

What works are being done?

The CBD Footpath replacement program will see the pavers and kerb progressively replaced along Main Street. The pavers are being replaced with concrete footpath, bordered by bluestone pavers with rustic brick banding – the same theme as used in Stage 1 works at Cook Street Plaza. The project emphasises pedestrian thoroughfare and walkability. 

Stormwater pipes under the footpath are being replaced, there will be a new concrete kerb installed, and compliant disabled parking spaces and loading zones will be installed.

Works also include further improvements like green scaping by built in garden beds and new traffic signs and line marking.

The pedestrian crossing at the eastern end of Main Street will be upgraded to a raised pedestrian crossing with improved gardens and lighting.

Improved accessible parking spaces and relocation of loading zones will also be installed to current standards making it easier for the community to use.

Why are the works being done?

Revamping and modernising of the Main Street façade has not been undertaken for a number of years, and these improvements will revitalise the look of Main Street, attracting more businesses to the area. This in turn will improve the vibrancy of the street atmosphere and expand on shopping opportunities for the community. 

The existing pavers are outdated, and reached the end of their useful life, becoming slippery in wet weather.  Replacing the pavers modern concrete with bluestone paving and brick banding will further improve the safety of the community.   

The gradient of the existing footpath and parking access ramps are too steep and don’t comply with current accessibility standards.  The design level of the new footpath will make Main Street easier to walk along for people with mobility issues. 

Council further took the opportunity to address the traffic issues and near miss conflicts between pedestrians and vehicles at the pedestrian crossing as part of this project. 

 

What are the major changes?

The most noticeable changes will include concrete replacing pavers to lighten the appearance of the street.   

The disabled parking space and loading zone on the southern side of Main Street has been relocated to the western end of the block, near Eskbank Street.  This was to enable a ramp to be placed that meets current standards.  Whilst this is further away from the current one located in the middle of the block, it will be balanced by the improvements in the gradient to the footpath, making is easier for mobility impaired community members to travel further distances. 

The eastern end of the southern side of the block needs some major relevelling work and will result in a higher double kerb.  To minimise trip and fall incidents, low level green scaped garden beds will be installed to soften the appearance, as well as encourage pedestrians to utilise the built-in steps at selected safe locations. 

The trailed traffic island at the intersection of Main Street and Bridge Street has proven successful in reducing the number of near miss collisions and will be permanently installed as part of this work.  The island will be a larger garden bed, again, adding to the landscaping areas of the project. 

A raised pedestrian crossing will also be a major change to the area, and increase the visibility of pedestrians waiting to cross. 

When will the work commence and how long will the project take?

Surveying works for the project are ongoing as of 2nd of December with a short break over the Christmas period. It is expected that works will progress toward Eskbank Street over the first half of 2025 and works are scheduled to be completed at the end of June 2025. 

Why has the Federal grant funding for the Main Street upgrade expired?

Eligibility for this grant funding has expired as resourcing and budgetary restraints restricted Councils ability to complete project planning and commence construction. 

Specifically, the Council had to allocate scarce project management resources towards projects with more imminent impacts on the community including the seven-natural disaster declarations.  The Council has also had difficulty retaining an ongoing Project Managers for the Main Street upgrade because of a competitive employment market.  

What does the loss of Federal Funding mean for the Main Street upgrade?

The expiration of this Federal funding means that, the project has had to be re-scoped to reflect the available funding. The Federal funding for this project was just one component of this project.  

The Council will still be delivering the footpath upgrade between Bridge Street and Eskbank Street commencing with the northern (railway) side and continuing with the southern (Mort Street) side once additional funding has been secured.    This Eskbank to Bridge Street section has been selected based on the greater risk posed to pedestrians by uneven pavers in this part of main street to ensure that priority work is done in the interest of safety.

The Council will advocate to the Federal Government to reinstate the funding for the continuation of the project from Eskbank Street to Cook Street and is also developing a grant application for other Australian Government and State Government funding streams. 

What measures is Council putting in to avoid this occurring in future.

A Project delivery oversight group has been established by Council to ensure comprehensive governance of all projects being delivered by Council, including projects funded by both state and federal Governments. Already this group is leading changes to Council’s project management processes. Continued reporting will also ensure that Councillors are informed directly on the delivery programs and risks with key projects. The Council has also increased the capacity of the infrastructure project management team to meet grant project delivery timeframes and commitments 

How will we be kept informed of this project and timelines?

The council will set up a dedicated webpage for this project which will detail the timelines and progress of the project.

Regular updates will be posted on Council’s Facebook page @LithgowCityCouncil and included in Council’s weekly subscriber eNewsletter, Council Connections. You can subscribe via the www.ourplaceourfuture.lithgow.com website.
Periodic updates will be included in the Council Community Update published monthly in the Lithgow Mercury and Village Voice.

Where appropriate, radio advertising will be used to inform of any additional disruption to the community such as temporary street closures.

How will Main Street businesses be kept informed of this project and timelines?

Council’s Project Manager will liaise with individual businesses on a regular basis and will identify how they wish to receive project updates in addition to the means outlined above.

 

How will the community be impacted? 

As with all projects, impacts to the community are expected especially during the construction phase. 

Some impacts to be expected are: 

  • Temporary relocation of the bus zone during construction.  Bus services will still run as scheduled, just the pickup / drop off location will be temporarily moved out of the construction zone. 
  • Reduced parking in Main Street.  As works roll along the street, certain locations will be blocked off as part of the construction zone.  This will limit the parking available in Main Street, with parking still being available at the public car parks in Railway Parade and Mort Street during works 
  • Changed traffic conditions.  Traffic controllers will be operational at the intersection of Main Street and Bridge Street during works, and motorists are advised to either take alternative routes of travel, and expect delays 
  • General construction noise / dust.  With any construction project, some level of construction noise and dust is to be expected.  These will be kept to a minimum, and monitored by the Contractor to ensure both noise and dust are not excessive. 
  • Changed pedestrian paths.  During works, safe passage of pedestrians will be provided around the work site, either via a road shoulder detour or temporary crossing to the other side of the road.   

These impacts are a necessary part of construction, and can not be avoided.  All care is taken by both Council and the Contractor in planning works to ensure that both the community and business impacts are kept to a minimum. 

How much is this project costing?

The project is predominantly grant funded with $1.5m from the State Government and The Council is contributing $800k in the 2024/25 Operational Plan funded from Special Parking Rate levies held in reserve. 

You announced the grant funding for this project in 2022. Why has it taken so long to get to this stage?

The Council received a $2m grant in 2022 from the State Government which relied upon Council matching the fund dollar for dollar. The Council had also secured funding from the Federal Government which expired in June 2024 which resulted in the project needing to be re-scoped.  

Why are you spending $4.5m doing this project and not spending the money to fix roads?

Grant funding from Governments can only be spent on the project that it was received for. It cannot be used for another project or purpose. 

CBD Businesses pay a parking special rate. What is this used for?

The special rate for parking for 151 CBD properties has continued within the designated area of Lithgow. At the Council meeting held on 26 November 2018 it was resolved:
18 – 349 RESOLVED
THAT Council take the following action from the 2019/20 financial year:

  1. Utilise the parking special rate for Lithgow CBD capital works and maintenance.
  2. Determine a specific program of works and activities which will be funded from the parking special rate for inclusion in each year’s Operational Plan (Revenue Policy).
  3. Any parking special rate funds not utilised in a financial year be placed in an internally restricted reserve for future Lithgow CBD capital works and maintenance.
  4. That the outcome of the program is reported to the Council annually and that the program is reviewed in 5 years.

The ad valorem rate and estimated yield is provided below.
The remaining Parking Special Rate income will be allocated to the Main Street Revitalisation project as a co-contribution for the grant funded project. Any parking special rate funds not utilised will be placed in an internally restricted reserve for future Lithgow CBD capital works and maintenance”.
The review of the Parking Special Rate is due for completion by 30 June 2024.

Special Parking Rate Table

How much does Council have in reserves for ongoing capital works for the CBD?

Council holds $500Kin reserves for ongoing CBD capital works. The funds were specifically set aside to build a grant funding co-contribution for the Main Street Upgrade project.

Will the Council install parking meters as a revenue stream and a way to pay for improvements to the CBD?

The council is not considering the installation of parking meters as part of this project.

The pavers in Main Street need to be made safe; the ramps at intersections from the footpath to the road are slippery in wet weather and some pavers are sitting up creating a trip hazard. How do you plan to fix this?

Stage 2 will see the pavers and kerb replaced between Cook Street and Bridge Street with shotblast concrete interspersed with heritage brick banding and bluestone edges. The project emphasises pedestrian thoroughfare and walkability. A specific outcome of this work will be the reconstruction of all pram ramps that meet current accessibility standards. 

When will you be renewing the Cook Street to Lithgow Street footpath?

The Main Street Restoration Project is a multi-stage project with funding of later stages still to be secured. The renewal of the footpath between Cook Street and Lithgow Street is part of the Master Action Plan. The process will commence once funding is secured.

Will businesses in the Cook Street to Lithgow Street Section of Main Street also be consulted prior to commencement of this section?

All CBD businesses are invited to provide feedback on Stage 2 of the project. This will inform the final look and feel of the Entire length of Main Street from Lithgow Street to Bridge Street.

The step up to the kerb is too high, how will this be improved?

The existing brick kerb is 200mm high which is above the standard 150mm. Kerb stones come in different sizes depending on their intended use. Standard sizes can range from 150mm to 300mm in height. The height of 200mm kerb stones will be used as it is needed to incorporate the outlets for rainwater from the awnings. Part of the scope of work for the footpath renewal will be to raise the outlets by 50mm to accommodate a new asphalt road surface as part of a future stage in the Main Street upgrade. Once the new surface is installed, the height of the kerb will be reduced to 150mm.

The Main Street Restoration Project is a multi-stage project with funding of later stages still to be secured. Asphalting of the concrete road is reliant upon the footpath being fully replaced between Bridge Street and Lithgow Street.

When will you replace the concrete road pavement with asphalt?

Funding for this later stage of the Main Street upgrade is still to be secured. The first step is the upgrade of the entire footpath, kerb & gutter, drainage and existing inground services. Asphalting of the concrete road is reliant upon the footpath being fully replaced between Bridge Street and Lithgow Street.

How much space will the planters take up? Will I hit them with my car door?

Planters currently exist on Main Street and do not interfere with entering and exiting your car. The new proposed planters will be similar in size to the existing planters.

Will the Council be installing EV charging points in Main Street?

The EV Charging Strategy was developed in collaboration with the Lithgow Community Power Project by the UTS Institute for Sustainable Futures in 2022 – Lithgow’s Electric Car Parks – An EV charging strategy for the Lithgow LGA and Main Street Precinct. The Strategy provides a framework for a consistent, community-driven approach to the deployment of EV destination charging infrastructure by Council and third-party service providers.

The Strategy sets out a long-term vision (10 years) with a short-term (3 years) and Implementation Plan for how publicly accessible EV charging infrastructure will be deployed within the Lithgow LGA. The resulting services are intended to benefit residents, visitors, and businesses with an initial focus on the Lithgow CBD precinct.

A key goal of the Council is to ensure that there is adequate charging infrastructure to support EV users wanting to make the best use of their time. The Council is currently working with NRMA (National Road and Motorist Association) on a project to install an EV Charging Station in the Eskbank Street Carpark, not Main Street. This location will enable visitors to take advantage of our cafes and shops whilst their vehicle is charging. Council executed the Section 88B instrument in December, formalising the power easement creation. The chargers will be commissioned early in the new year. 

How is Council going to improve accessibility in Main Street?

The Main Street Revitalisation Action Plan process has identified that the Main Street entry could be significantly improved to provide a more generous civic access which could improve night comfort and security.
All pram ramps will also be replaced to ensure compliance with modern standards, and disabled parking spaces will also be upgraded to ensure they meet current standards regarding length, width, crossfall and footpath accessibility.

All pram ramps will also be replaced to ensure compliance with modern standards, and disabled parking spaces will also be upgraded to ensure they meet current standards regarding length, width, crossfall and footpath accessibility. This will occur along the northern side of Main Street between Bridge Street and Eskbank Street as oart of the Stage 2a works. 

Why is the council replacing the current slippery pavers with concrete and not extending the bluestone pavers in front of the post office along the Main Street?

A study was performed to evaluate the performance of different surfaces for the Main Street footpath which included bluestone pavers compared to concrete. The study concluded that concrete outperformed the bluestone pavers in slip resistance and durability.

It is also a simpler process to reinstate slip resistance of concrete over time with sand blasting, acid etching, or similar.

The materials that will be used for this project are still in keeping with the heritage and the surrounding environment of Lithgow. The concrete pavement lifts and lightens the Main Street and is softened by heritage brick bands and bluestone which speak to the heritage architecture and fabric of Lithgow.

The use of concrete also allows for easier cleaning and maintenance. Overall, the cost to construct and whole of life cost is less than it would be for installation and ongoing maintenance of the bluestone pavers for the entire footpath.

The handrails from the elevated footpath to road between Cook Street and Bridge Street are not suitable particularly for a taller person.

The new handrails have been designed to comply with the current Australian Standards (AS1428) – “The top of the handrail must be not less than 865mm or greater than 1000mm from the nosing of a stair or the plane of the finished floor level on a ramp, walkway or landing”.

Will the Council be planting more street trees in the CBD?

Plantings will be included at the intersections of Eskbank Street and Bridge Streets. Bridge Street will become a focal entry to the Main Street like the Lithgow Street intersection.

Three concepts have been developed for the Eskbank Street intersection to soften and make this a ‘green’ focal point.

Pot planters and trellis planters to be placed against large blank walls or around awning posts will be placed at intervals along the Main Street.

Will there be on-street dining for cafes like in other CBDs with planters and shelters?

The council will make every effort to consult with businesses to establish needs in relation to on-street dining. Overall, this project is being delivered to make Main Street a more attractive place to shop and conduct business. On street trading contributes to a more vibrant, lively and accommodating space. Contributing to the potential for on-street trading strongly features as part of this project.

What is the cost of ongoing maintenance for the planters and gardens?

The council will be working with the retailers and businesses on Main Street to ascertain their level of interest in maintaining planter pots.

The council has also commenced a program of replacing ‘high maintenance’ street tree species with less labor-intensive species throughout the LGA. This will enable Council to divert Parks & Garden staff from pruning programs to other projects such as maintaining green spaces in the CBD. To date, this work has already occurred on Mort Street, Lithgow, with several ‘mop tops’ being replaced with a more appropriate species.

Will the Council ensure the permanent plantings at intersections and Cook Street Plaza and Pioneer Park are maintained?

Council will be considering a detailed design of the permanent plantings which will include low-maintenance species and the development of maintenance schedules to ensure that greenspaces are always looking their best. Engagement with Council’s employed horticulturalists will occur as part of the broader consultation for this project to ensure this aspect of the yearly maintenance is appropriately addressed.

It should be noted that there may be times when the timeframes may need to be adjusted due to unforeseen circumstances. The infrastructure under the surface in Main Street is ageing and something unplanned may be found. In such cases, Council will work with business and keep everyone informed of any deviations or extensions to timeframes as the project progresses. 

How will you reduce the impact of disruption on businesses?

The council acknowledges that businesses and the community may be disrupted during the project. However, it is intended that the project will be undertaken in stages to reduce any inconvenience. The council will not be ripping the footpath up all in one go. The project will be staged so that the work is undertaken in small sections and then progressed forward. All businesses will be aware of when works will be undertaken in front of them so they can plan their trading and inform their customers/clients.

It should be noted that there may be times when the timeframes may need to be adjusted due to unforeseen circumstances. The infrastructure under the surface in Main Street is ageing and something unplanned may be found. In such cases, Council will work with business and keep everyone informed of any deviations or extensions to timeframes as the project progresses.

What if I have an appointment or wish to go to a certain shop and the footpath is being ripped up in front of that business?

Businesses will be aware of when the footpath renewal is going to be undertaken in front of their shop or business. Every effort will be made to minimise impact to businesses during high-traffic periods. A schedule of work will be available in advance so they will be able to plan for this disruption and keep their loyal customers or clients informed of any changes to appointments or their hours of service.

What about events such as Beatlesfest, Halloween and Christmas – will they be cancelled or only held in the bottom half of the Main Street?

No, Council has factored in ‘hold points’ in the project timeline. This will mean that for a short period preceding and during these events, the upgrade project will temporarily stop. This will enable all businesses to take advantage of visitor trading during events and the CBD will be promoted as “open for business”.

Have you factored in delays due to weather conditions?

Yes, weather conditions will be factored into the project. One advantage of this project is the awnings will provide under-cover construction enabling work to continue during adverse weather.

I live above the shops in Main Street – will you be undertaking ‘out of hours’ work?

All work is expected to be undertaken during normal working hours of 7.00am to 6.00pm weekdays, and 8.00am to 1.00pm Saturdays. No work outside these hours, including Sunday or Public holidays will be undertaken without Council permission, and Council will letterbox drop residents and businesses advice if this is to occur, However if there is a temporary change to the hours of operation, Council will ensure that all Main Street residents are informed in advance. 

The original CBD Revitalisation Action Plan was developed in 2015. Has the design intent been updated since then?

Yes, as part of this stage of the project, the Council engaged the landscape architects, Civic Designers and Structural engineers who have been involved with the project since its conception, to review the original masterplan. The materials that will be used for this project are still in keeping with the heritage setting and the surrounding environment of Lithgow. The concrete pavement lifts and lightens the Main Street and is softened by heritage brick bands and bluestone which speak to the heritage architecture and fabric of Lithgow. The greening will mirror the surrounding bush clad hills that can be seen from anywhere in the CBD. 

I heard that the Council lost money for this project, is this true and if so, why did this happen?

 Eligibility for this grant funding  expired as resourcing and budgetary restraints restricted Councils ability to complete project planning and commence construction.  

Specifically, the Council had to allocate scarce project management resources towards projects with more imminent impacts on the community including the seven-natural disaster declarations.  

 The Council has also had difficulty retaining an ongoing Project Managers for the Main Street upgrade because of a competitive employment market.   

What does this mean for the Main Street upgrade?

The expiration of this funding means that the project has had to be re-scoped to reflect the available funding. The Federal funding for this project was just one component of this project.    

The Council will still be delivering the footpath upgrade between Bridge Street and Eskbank Street, with the construction tender for this section released in  September 2024 and negotiated with a preferred contractor, with contracts signed in December 2024. 

This section has been selected based on the greater risk posed to pedestrians by uneven pavers in this part of main street to ensure that priority work is done in the interest of safety.  

The Council will advocate to the Federal Government to reinstate the funding for the continuation of the project from Eskbank Street to Cook Street and is also developing a grant application for other Australian Government funding streams.

What measures is Council putting in to avoid this occurring in future.

A Project delivery oversight group has been established by Council to ensure comprehensive governance of all projects being delivered by Council, including projects funded by both state and federal Governments. Already this group is leading changes to Council’s project management processes. Continued reporting will also ensure that Councillors are informed directly on the delivery programs and risks with key projects.  

The Council has also increased the capacity of the infrastructure project management team to meet grant project delivery timeframes and commitments. 

Project History

Planning on the project commenced in 2016 with the adoption of the Lithgow CBD Revitalisation Action Plan, identifying Main Street from Bridge Street to Cook Street Plaza as the priority areas for action. 

Stage 1 of the project involved revitalisation of Cook Street Plaza and Main Street / Eskbank Street intersections, and was completed in 2019 

As part of Stage 1 works, a theme for finished materials was selected, being shot blast finished concrete with recycled brick banding and bluestone paving edge stripThis theme was chosen to reflect the ties to Lithgow’s industrial heritage, whilst also being visually attractive, modern, and easily maintained. 

Draft designs for Stage 2 works were present to Councillors and the public in 2023, with formal and final design work commencing mid-year. 

Works were designed to ensure that the reconstructed footpath meets current accessibility legislation and standards.  This was very challenging due to the inconsistent and non-compliant existing levels, and required a number of attempts at redesign to ensure the final design had a streamlined flow and was safe and accessible 

The final design includes a number of inbuilt planter gardens on the southern (Mort Street) side with staged step access to prevent the need for a handrail at this location.  This has resulted in the accessible parking space being moved further west, toward the Eskbank Street intersection.  This allows for an on-road access ramp to be constructed for dual use by accessible vehicles as well as delivery vehicles, with the loading zone also being moved for easy footpath access. 

The level of the footpath on the northern (railway line) side were less challenging, but the theme of garden plantings will be continued for consistency.